Jerusalem / Hebron Road Project ( Section 2) TT1-3

The works comprise the redevelopment of Section 3 of Jerusalem- Hebron Road between Sta. 4+700 and Sta. 6+999.64, a distance of approximately 2,300m. The rehabilitation will provide 4 lanes carriageway with paved Sidewalks, each width will be 3.5m and the sidewalk width will be 1.2m. Construction of the works will involve overlay and the reconstruction of extension for both sides of the existing road to become 4 lanes carriage way from Sta. 4+700 to 6+999.64. Utilities works will include providing surface storm water drainage, street lighting and development of other facilities…etc.

Services Performed Client Contract No. Cons. Cost Mill. US$ Year
Design Review & Supervision Consultancy Services Bethlehem 2000 Project Authority B2000/IS/ TT1-3 2 1999